In one line
Job costing = every cost, coded to the job (and phase, cost code, cost type) that caused it, compared against that job’s budget.
Job costing, defined
Job costing (job order costing) traces individual costs directly to a final job or service. It is the standard method for businesses whose work is custom and project-based, which is why textbooks use building contractors as the example.
The opposite is process costing, which averages costs across identical units — see job costing vs process costing. A contractor’s question is never “what does an average unit cost?” but “is Job 2041 going to make the margin we bid?”
The four coding dimensions: job, phase, cost code, cost type
Most construction job-cost systems code each cost to a job, a phase within the job, a cost code for the scope of work, and a cost type such as labor or material.
| Dimension | What it answers | Example |
|---|---|---|
| Job | Which project or contract? | 2041 — Riverside medical office |
| Phase | Which stage or area of the job? | 03 — Rough-in, Level 2 |
| Cost code | Which scope of work? | 09-2900 — Gypsum board (CSI MasterFormat-style) |
| Cost type | What kind of cost? | Labor, material, subcontract, equipment, other |
Budget, committed, actual, and projected cost
Job costing is only useful if it shows four numbers side by side for each code: the budget, what you have committed to spend, what has actually been incurred, and what the line is projected to cost at completion.
| Number | Where it comes from | Why it matters |
|---|---|---|
| Budget | The estimate, revised by approved change orders | The baseline margin was bid on |
| Committed cost | Signed subcontracts, purchase orders, approved change orders | Money you are already obligated to spend, invoiced or not |
| Actual cost | Approved vendor bills, payroll, equipment charges | What has been incurred to date |
| Projected cost | Actual plus estimated cost to complete (at least the committed amount) | Shows fade before the job closes |
Committed cost is the number most small contractors are missing: a $180,000 subcontract signed today does not show up in actual cost until the first bill arrives, but it is already spent. See the committed cost definition.
A worked example
A $1.2 million job with a $1.02 million cost budget looks healthy on actuals alone until committed cost and cost to complete are added.
| Cost code | Budget | Committed | Actual to date | Projected |
|---|---|---|---|---|
| 03-3000 Concrete | $210,000 | $225,000 | $225,000 | $225,000 |
| 09-2900 Drywall (sub) | $180,000 | $188,000 | $94,000 | $188,000 |
| 26-0500 Electrical (sub) | $240,000 | $240,000 | $60,000 | $240,000 |
| 01-5000 General conditions | $390,000 | $40,000 | $170,000 | $400,000 |
| Total | $1,020,000 | $549,000 | $1,053,000 |
Projected cost is $33,000 over budget, so gross profit fades from $180,000 to $147,000 (15.0% to 12.3%). Actual cost alone — $549,000 against a $1,020,000 budget — would not have shown it. The $15,000 concrete overrun is already final, an $8,000 drywall change order was committed but never re-budgeted, and general conditions are trending $10,000 over.
Where AP fits: every bill is a job-cost entry
In construction, most actual cost arrives through accounts payable, so job-cost accuracy depends on each vendor bill being coded to the right job, phase, and cost code before it posts.
- 1Capture the bill and identify the vendor, job, and any purchase order or subcontract it bills against.
- 2Code every line to job, phase, cost code, and cost type — split lines that cover more than one code.
- 3Match it to the commitment so overbilling against a subcontract or PO is caught before approval.
- 4Route it to the project manager who can confirm the work was done.
- 5Withhold retainage at contract terms and check lien-waiver and insurance requirements before payment.
- 6Post the coded bill to the accounting system so the job-cost report and the general ledger agree.
Miscoded bills are the most common reason job-cost reports stop being trusted. Put a number on it with the job-cost error impact calculator.
Job costing in QuickBooks
QuickBooks Online can job cost with customers and Projects, classes, and products and services used as cost codes, but it has no native phase, cost-type, or committed-cost structure.
The full setup — and what to do about the gaps — is in job costing in QuickBooks Online for construction bills. If you are deciding whether QuickBooks is still enough, read construction accounting software for QuickBooks users.
Reports job costing should produce
At minimum: a job-cost detail by code, a budget-vs-committed-vs-actual summary per job, and a WIP schedule across all open jobs.
- Job-cost detail — every transaction on a job, by cost code, traceable to the source bill.
- Budget vs committed vs actual vs projected — per job, per code.
- WIP schedule — percent complete, earned revenue, and over/under billing across open jobs.
- Unbilled and retainage reports — what is earned but not billed, and what is held.
Aequo Build
How Aequo Build handles job costing on top of QuickBooks Online
Aequo Build codes invoice and purchase-order lines to job, job-specific phase, cost code, and cost type. Subcontracts, purchase orders, and approved change orders count as committed cost; approved, coded invoices post actual cost entries linked back to the source document, and re-approval or rejection reverses and reposts them so totals stay traceable.
Approved bills sync to QuickBooks Online with their GL accounts (and a class where you map one). Phase, cost code, and cost type detail stays in Aequo Build rather than being written to QuickBooks.
Frequently asked questions
What is job costing in simple terms?
Recording every cost against the job that caused it, so you can see what each project actually cost compared with what you estimated.
What are the main components of job costing?
Direct labor, direct materials, subcontract costs, equipment, and an allocation of overhead — coded by job, phase, cost code, and cost type, and compared against the budget.
What is the difference between a cost code and a cost type?
A cost code describes the scope of work (for example drywall or site concrete). A cost type describes the kind of cost (labor, material, subcontract, equipment). The same cost code usually has costs of several types.
What is committed cost in job costing?
The total you are contractually obligated to spend on a job through signed subcontracts, purchase orders, and approved change orders, whether or not the bills have arrived yet.
Can you do construction job costing in QuickBooks Online?
Partly. QuickBooks Online supports tracking costs by customer or project, class, and product or service, but not phases, cost types, or committed cost natively. Many contractors add a construction AP or job-cost tool on top.