Subcontractor compliance checklist

Before a subcontractor starts work, you need a signed subcontract, a W-9, a certificate of insurance that meets your requirements, proof of workers’ compensation, and a verified licence. Before every payment, re-check insurance, collect the lien waiver for that payment, withhold retainage, and — on prevailing-wage jobs — confirm certified payroll is in. Print this checklist or use it as your AP payment gate.

Last updated · Aequo AP editorial team

Before the subcontractor starts work

Collect and verify these documents before the first day on site; most of them are also preconditions for the first payment.

  • Signed subcontractScope, price, retainage rate and release terms, insurance and indemnity requirements, lien-waiver requirements, and the right to withhold payment for non-compliance.
  • Form W-9Legal name, tax classification, and taxpayer identification number (TIN). Needed for 1099 reporting; without a TIN you may have to apply backup withholding.
  • Certificate of insurance (COI)Coverage types and limits that meet the subcontract, policy dates covering the work, correct named insured and certificate holder.
  • Additional-insured endorsementWhere the subcontract requires it, the policy endorsement itself — the certificate alone does not amend the policy.
  • Workers’ compensationProof of coverage, or the exemption documentation your state accepts.
  • Contractor licenceLicence number, classification, and status verified on the state (or local) licensing board’s lookup for the trade and location of the work.
  • Bank details verifiedBank account confirmed by a call-back to a known phone number, never by reply to the email that sent it.
  • Prevailing-wage flow-down (if applicable)On Davis-Bacon or state prevailing-wage jobs: the wage determination and certified payroll obligations included in the subcontract.

Before every payment

Re-check the items that expire or change between pay periods; this is where most compliance failures happen.

  • Invoice or pay application approvedWork verified by the project manager; billed amount within the subcontract and approved change orders.
  • Retainage withheldAt the subcontract rate (and any statutory cap), recorded as retainage payable — not netted inside A/P.
  • Lien waiver for this paymentConditional waiver for the amount being paid now; unconditional waiver for the prior payment once it has cleared — on your state’s statutory form where one is required.
  • Insurance still currentNo certificate expired or below the required limit since the last payment.
  • Certified payroll received (if applicable)Weekly certified payrolls with signed Statement of Compliance for every week the sub worked on a covered job.
  • Lower-tier waivers (if required)Waivers from the sub’s own suppliers and sub-subcontractors on larger contracts.
  • No bank-detail change pending verificationAny change since the last payment confirmed by call-back before funds move.

At closeout and retainage release

Release final retainage only after the work is accepted and the final paperwork is in.

  • Punch list complete and work acceptedWritten acceptance by the project manager or owner as the subcontract requires.
  • Final conditional and unconditional lien waiversCovering the full contract amount including retainage.
  • Closeout documentsWarranties, as-builts, O&M manuals, and attic stock where specified.
  • Retainage release approvedPosted against the retainage payable balance, within any statutory release deadline.
  • Year-end 1099 dataPayments to the subcontractor reconciled to the W-9 on file for 1099-NEC reporting.

Detailed guides for each item

Each checklist item has a deeper guide covering the rules and the workflow.

Aequo Build

Turn the checklist into a payment gate with Aequo Build

Aequo Build checks several of these items automatically when you start a payment: an approved invoice, insurance certificates that are current and meet your requirements, a received W-9 for 1099-eligible vendors, and — when you turn on blocking for non-compliant payments — a verified lien waiver. Subcontractors can upload COIs and lien waivers and submit W-9 details through a portal link, and retainage is withheld at the subcontract rate when the invoice is approved. Licence checks, closeout documents, and certified payroll remain manual items on this list.

Frequently asked questions

What documents do you need from a subcontractor?

At minimum a signed subcontract, a W-9, a certificate of insurance meeting your requirements, workers’ compensation proof or exemption, and licence details. Then a lien waiver with each payment and final waivers at closeout.

Do I need a W-9 from every subcontractor?

You should request one from every subcontractor you may need to report on Form 1099-NEC. The W-9 gives you the correct name and TIN; if a payee fails to provide a TIN you may be required to apply backup withholding.

How often should subcontractor compliance be checked?

Onboarding documents once (and on renewal), payment-specific items before every payment, and final items at closeout.

Related guides and tools

Sources

This checklist reflects common practice. It is not legal, tax, or insurance advice; requirements depend on your contracts, your state, and the project.

  1. IRS — About Form W-9, Request for Taxpayer Identification Number and Certification
  2. IRS — Backup withholding
  3. IRS — Form 1099-NEC and independent contractors (FAQ)
  4. ACORD 25 Certificate of Liability Insurance, 2016/03 specimen (hosted by NY Department of Financial Services)
  5. U.S. Department of Labor — Form WH-347, Payroll (for contractors’ optional use)

Part of the Construction AP Knowledge Centre.