Progress payment waivers

What is a partial lien waiver?

A partial lien waiver, also called a progress waiver, gives up lien rights only for a progress payment, covering work through a stated date or amount. Later work, retention and unpaid change orders stay protected. Use a conditional partial waiver while payment is pending and an unconditional one only after the money has cleared.

This guide covers the progress-payment side of the waiver exchange: what a partial waiver leaves open, which version to collect at each step of a monthly pay application cycle, and the state forms that apply. For the last payment on a job, see the final lien waiver guide.

Last updated · By the Aequo AP construction team

What a partial lien waiver covers, and what it does not

A partial waiver releases lien rights for one payment, for work through a stated date. Anything after that date, retention, unpaid change orders and anything listed as an exception stay protected.

What a partial lien waiver covers and leaves open
Covered by the partial waiverNot covered (claimant keeps lien rights)
Time periodWork, materials and services furnished through the through dateAnything furnished after the through date
MoneyThe payment named on the waiverRetention withheld from that and earlier payments
ChangesApproved change-order work included in the paymentPending or unapproved change orders and extra work
DisputesNothing in dispute, if the exceptions line is usedDisputed amounts and earlier unpaid billings listed under exceptions

Statutory forms build these limits in. Arizona's progress forms release rights for work furnished “through ______ only and does not cover any retention, pending modifications and changes or items furnished after that date.” Wyoming's single statutory form is progress-style and preserves rights to retainage and later unpaid work.

The exceptions line is how a claimant keeps anything else open. Our conditional progress and unconditional progress templates prompt for it: disputed change orders, retention, and unpaid prior invoices. Where a state prescribes the form, use its wording rather than adding your own.

Partial vs final: a partial waiver is one receipt in a series, and the claimant keeps its rights for everything still to be paid. A final lien waiver is the last one and releases everything on the job apart from its listed exceptions, which is why retention and late change orders are usually settled there.

Conditional vs unconditional partial lien waivers

A conditional partial waiver only takes effect once the payment is received and clears; an unconditional partial waiver takes effect when it is signed. Exchange the conditional one for the payment and collect the unconditional one after the money clears.

Conditional and unconditional partial lien waivers compared
Conditional partial (progress) waiverUnconditional partial (progress) waiver
Takes effectWhen the stated payment is received and clearsOn signing and delivery
When it is exchangedWith the pay application, before or at paymentAfter the payment clears, often with the next pay application
AmountThe payment about to be madeThe payment actually received
If the payment failsGenerally has no effect; lien rights remainMay still be enforceable against the claimant
Statutory namesConditional Waiver and Release on Progress Payment; Partial Conditional Waiver (MI)Unconditional Waiver and Release on Progress Payment; Partial Unconditional Waiver (MI)

Not every state uses the split. Florida, Georgia, Massachusetts, Mississippi, Utah and Wyoming each have a single statutory progress form; Utah's is a conditional form, and Georgia and Mississippi set their own rules on when theirs takes effect (see the state table below). The general comparison, with a bounced-check example, is in conditional vs unconditional lien waivers.

Worked example: partial waivers across a monthly pay app cycle

Each month the subcontractor sends a conditional waiver for the payment it is requesting and an unconditional waiver for the previous payment, once that has cleared. Retention and disputed change orders stay outside every partial waiver.

Illustrative only: the subcontract, amounts and 10% retention rate are invented for this example. Your retention rate, billing dates and waiver amounts come from your contract and your state's form.

A drywall subcontractor bills a general contractor monthly, with each pay application covering work through month-end. The subcontract withholds 10% retention, and each waiver is for the net payment the subcontractor will actually receive.

Illustrative monthly pay applications and the partial waivers collected with each
Pay appWork throughBilled this periodRetention withheld (10%)Net paymentWaivers collected with this pay app
No. 1March 31$60,000$6,000$54,000Conditional progress waiver: $54,000 through March 31
No. 2April 30$90,000$9,000$81,000Conditional: $81,000 through April 30. Unconditional: $54,000 through March 31 (No. 1 has cleared)
No. 3May 31$75,000$7,500$67,500Conditional: $67,500 through May 31. Unconditional: $81,000 through April 30 (No. 2 has cleared)

After pay app No. 3 is paid, the general contractor's file should show unconditional waivers through April 30, a conditional waiver through May 31 waiting on its payment to clear, and $22,500 of retention that no partial waiver covers. Suppose the subcontractor has also submitted a $12,000 change order that is not yet approved: it lists that amount under exceptions on each waiver, and it stays open until it is approved and paid or settled at closeout with the final waiver.

On AIA-style billing, each period's amounts come from the G702 Application and Certificate for Payment, which shows work completed to date, retainage, previous payments and the current payment due. See the G702/G703 worked example and the retainage guide.

In what order are partial waivers exchanged?

Conditional with the pay application, payment against it, then unconditional once the funds clear. The unconditional waiver for one payment usually arrives with the next pay application.

  1. With the pay application: the subcontractor or supplier sends a conditional progress waiver for the amount of this payment, through the billing date.
  2. Before paying: check the waiver type, amount, through date, project and signature, and that it uses the statutory form where one applies.
  3. At payment: release the payment against the verified conditional waiver.
  4. After the funds clear: collect an unconditional progress waiver for the amount received, through the same date. Many payers make it a condition of the next payment.
  5. At closeout: the same exchange happens with conditional and then unconditional final waivers, usually alongside the retention release.

In Georgia and Mississippi, where the statutory waiver is not split into conditional and unconditional versions, a claimant who signs and is not paid has to file an Affidavit of Nonpayment within the statutory window: otherwise, in Georgia the waiver becomes effective 90 days after signing, and in Mississippi the amount is conclusively deemed paid 60 days after signing.

Which states have statutory partial (progress) lien waiver forms?

11 states have a statutory form for progress or partial payments. In states where the form is mandatory, a waiver that does not substantially follow it may be unenforceable.

States with statutory progress-payment lien waiver forms
StateStatutory progress form(s)What to know
Arizona
  • Conditional Waiver and Release on Progress Payment
  • Unconditional Waiver and Release on Progress Payment
Mandatory forms. A conditional release protects the payer only if there is evidence of payment.
California
  • Conditional Waiver and Release on Progress Payment (§8132)
  • Unconditional Waiver and Release on Progress Payment (§8134)
Mandatory forms. A conditional waiver is effective only on the claimant’s receipt of payment (§8124).
Florida
  • Waiver and Release of Lien upon Progress Payment (§713.20(4))
One progress form, optional for the lienor. Rights may be waived only for work already furnished, and a waiver given for a check may be conditioned on that check being paid.
Georgia
  • Waiver and Release of Lien and Payment Bond Rights upon Interim Payment
Mandatory form with no conditional version. A signed waiver takes effect on the earliest of receipt of funds, a written acknowledgment of payment, or 90 days after signing, unless the claimant first files an Affidavit of Nonpayment.
Massachusetts
  • Partial Waiver and Subordination of Lien
Applies only to a partial waiver given by a party that has filed a notice of contract.
Michigan
  • Partial Unconditional Waiver
  • Partial Conditional Waiver
Mandatory forms. A partially paid claimant must provide a partial unconditional waiver on request.
Mississippi
  • Interim Waiver and Release upon Payment
Mandatory form with a notary jurat. The amount is conclusively deemed paid 60 days after signing unless the claimant files an Affidavit of Nonpayment first.
Nevada
  • Conditional Waiver and Release upon Progress Payment
  • Unconditional Waiver and Release upon Progress Payment
Mandatory forms. Unconditional forms must warn a claimant who has not been paid to use a conditional form.
Texas
  • Conditional Waiver and Release on Progress Payment
  • Unconditional Waiver and Release on Progress Payment
Mandatory forms. No one may require a claimant to sign an unconditional waiver until the payment is received in good and sufficient funds (§53.283).
Utah
  • Utah Conditional Waiver and Release upon Progress Payment
Optional form. If the payment check does not clear, the waiver is void and the claimant’s rights are preserved.
Wyoming
  • Lien Waiver
One statutory form, progress-style: it preserves rights to retainage and later unpaid work. It includes a notarial acknowledgment block.

Missouri's only statutory form is an unconditional final waiver for residential property, so it has no progress form. Statute citations and the full rules for each state are in lien waiver forms by state. Elsewhere, our free templates include a conditional progress waiver and an unconditional progress waiver.

Common partial lien waiver mistakes

Signing or demanding an unconditional waiver before the money clears, leaving gaps between through dates, missing sub-tier waivers, and amounts that do not match the payment.

  • Unconditional before funds clear. The claimant can lose lien rights for money it never received. In Texas, requiring it is prohibited.
  • Through-date gaps. When an unconditional waiver never arrives for one payment, that period rests on a conditional release while later months look complete. Check that every paid period has its unconditional waiver, through the same date as the conditional one.
  • Wrong amount. A waiver for the gross billing when the payment is net of retention, or for a figure that does not match the check, is hard to rely on. Match the amount to the payment it is exchanged for.
  • Treating a conditional waiver as final proof. Without the matching unconditional waiver, the file shows a release that depended on a payment you have not proved cleared.
  • Missing sub-tier waivers. Your direct subcontractor's waiver does not release its suppliers' or sub-subcontractors' rights.
  • Ignoring the exceptions line. A claimant that leaves a disputed change order off the exceptions risks waiving it; a payer that does not read the exceptions does not know what is still open.
  • Using a generic form in a statutory-form state. In Arizona, California, Georgia, Michigan, Mississippi, Nevada and Texas the statutory form is mandatory.

How general contractors track partial waivers across subs

Track waivers per payment, not per project: for every subcontractor payment, record the conditional waiver, the payment, and the unconditional waiver that closes it, with the amount and through date of each.

A working waiver log has, for each subcontractor and supplier on each job:

  • The pay application or invoice and the payment amount after retention.
  • The conditional waiver received: amount, through date, form, who checked it.
  • The payment date and whether the funds have cleared.
  • The unconditional waiver received for that payment, and when.
  • Open exceptions, retention held, and any sub-tier waivers required.

A spreadsheet can list these, but it cannot stop a payment going out before the waiver is in. With waiver enforcement on in Aequo Build, a payment started from Aequo gets a conditional progress waiver requirement for the net amount payable after retainage, through the invoice date, and is held until a reviewer verifies a waiver that covers it or an approver records an override with a reason. Once the invoice is fully paid, whether marked paid in Aequo or paid in QuickBooks Online, Aequo requests the matching unconditional waiver. Payments made outside Aequo are not held, and sub-tier waivers are not tracked. The collection workflow guide covers the full process and its limits, and the lien-waiver risk assessment scores your current controls. For notarization rules, see does a lien waiver need to be notarized.

Frequently asked questions

Is a partial lien waiver the same as a progress lien waiver?

Yes. Partial waiver, progress waiver and partial waiver of lien all describe a waiver tied to one progress payment rather than the whole job. Statutes use their own names: California, Texas and Arizona say “waiver and release on progress payment,” Michigan says “partial conditional” and “partial unconditional waiver,” and Georgia and Mississippi say “interim” payment.

Partial vs final lien waiver: what is the difference?

A partial waiver covers one progress payment for work through a stated date, and leaves retention, later work and unpaid changes open. A final waiver is exchanged for the last payment and releases everything left on the job except the exceptions written on it.

Does a partial lien waiver cover retainage?

Generally not. Arizona’s statutory progress forms say the release “does not cover any retention,” and Wyoming’s form preserves rights to retainage. Retention is normally released with the final payment and the final waiver. On a generic form, list retention under the exceptions so there is no doubt.

What amount goes on a partial lien waiver?

The amount of the payment it is exchanged for, not the contract sum or the total billed to date. Arizona’s unconditional progress form, for example, states that the claimant “has received a progress payment in the sum of” a stated amount. If retention is withheld, that payment is the net amount.

Can a general contractor require an unconditional partial waiver before paying?

It should not, and in Texas it may not: no one may require a claimant to sign an unconditional waiver unless the claimant has received that payment in good and sufficient funds. Collect the conditional waiver to release the payment, and the unconditional one after it clears.

Do partial lien waivers need to be notarized?

Usually not. Of the statutory progress forms, Mississippi’s includes a notary jurat and Wyoming’s a notarial acknowledgment block. Texas no longer requires notarization for original contracts entered into on or after January 1, 2022. A contract can still require it.

Do I need partial waivers from sub-tier subcontractors and suppliers?

On jobs where lower tiers have lien rights, yes. A partial waiver from your direct subcontractor only releases that subcontractor’s own rights; its suppliers and sub-subcontractors may still be able to file a lien for the same period.

Aequo Build

Stop paying subs before the waiver is in.

With waiver enforcement on, Aequo Build creates a conditional waiver requirement for each subcontractor payment you make from Aequo, holds that payment until a reviewer verifies the waiver or an approver records a reasoned override, escalates overdue requests to the subcontractor and your team, and requests the unconditional waiver once the invoice is paid. It works with QuickBooks Online.

Sources

Primary sources checked on November 9, 2026. Statutes change; always confirm against the current text.

  1. Arizona Revised Statutes §33-1008 (progress-payment forms: “through ___ only and does not cover any retention”)
  2. California Civil Code §8132 (conditional waiver and release on progress payment)
  3. California Civil Code §8134 (unconditional waiver and release on progress payment)
  4. California Civil Code §8124 (when a conditional waiver is effective; evidence of payment)
  5. Texas Property Code §§53.281–53.287 (progress forms; §53.283 unconditional waivers)
  6. Florida Statutes §713.20(2), (4) and (7) (no advance waiver; progress form; waiver conditioned on a check)
  7. O.C.G.A. §44-14-366 (Georgia interim waiver; 90-day Affidavit of Nonpayment) — via Justia
  8. MCL 570.1115 (Michigan partial conditional and unconditional waivers)
  9. Miss. Code §85-7-433 (interim waiver form; Affidavit of Nonpayment) — via Justia
  10. NRS 108.2457 (Nevada progress-payment forms)
  11. Utah Code §38-1a-802 (conditional waiver upon progress payment)
  12. W.S. §29-10-101(b) (Wyoming lien waiver form) — via Justia
  13. M.G.L. c. 254, §32 (Massachusetts partial waiver and subordination of lien)
  14. AIA Contract Documents — Instructions: G702–1992, Application and Certificate for Payment — work completed to date, retainage, previous payments and current payment due