What is the AIA G702?
The G702 (current edition G702–1992) is a one-page application in which the contractor states how much of the contract has been earned and how much is due now, and the architect certifies the amount the owner should pay.
AIA describes G702 as serving as both the contractor’s application and the architect’s certification. It is designed for projects where the contractor has a direct agreement with the owner, with payment procedures set out in AIA A201, General Conditions. The contractor signs it (and has it notarized where the contract calls for that), attaches the G703 and submits both to the architect. The architect may certify a different amount — initialing changed figures and attaching an explanation — and the owner pays the contractor the amount certified.
| Line | What it shows | Where the number comes from |
|---|---|---|
| 1 | Original contract sum | The signed contract |
| 2 | Net change by change orders | Approved change orders (additions minus deductions) |
| 3 | Contract sum to date | Line 1 ± line 2 |
| 4 | Total completed and stored to date | Column G total on the G703 |
| 5 | Retainage — (a) % of completed work, (b) % of stored material | 5a from G703 columns D + E; 5b from column F; total = column I total |
| 6 | Total earned less retainage | Line 4 − line 5 total |
| 7 | Less previous certificates for payment | Line 6 from the prior certificate |
| 8 | Current payment due | Line 6 − line 7 |
| 9 | Balance to finish, including retainage | Line 3 − line 6 |
What is the AIA G703?
The G703 Continuation Sheet lists each line of the schedule of values and tracks, per line, what has been billed before, what is billed this period, materials stored, percent complete, balance to finish and retainage.
AIA’s instructions say columns A–C should match the schedule of values the contractor submitted at the start of the project. Approved change orders are usually listed separately, at the end of the basic schedule or on their own sheet. Column I (retainage) is normally used only when the contract allows a different retainage rate per line.
| Column | Meaning |
|---|---|
| A | Item number |
| B | Description of work |
| C | Scheduled value |
| D | Work completed — from previous applications |
| E | Work completed — this period |
| F | Materials presently stored (not in D or E) |
| G | Total completed and stored to date (D + E + F) |
| % | Percent complete (G ÷ C) |
| H | Balance to finish (C − G) |
| I | Retainage (if variable rate) |
Worked example: a filled-in G702/G703-style pay application
On application No. 3 for a $1,025,000 contract with 10% retainage, the contractor has completed and stored $564,000 of work, holds $56,400 in retainage, was previously certified $274,500, and is owed $233,100 this period.
The project is fictional: an original contract of $1,000,000, one approved change order for $25,000 (parking-lot lighting) and 10% retainage on both completed work and stored materials. Two applications have already been paid. This period the contractor completed steel, concrete, MEP rough-in and part of the change-order work, and has roofing and mechanical equipment stored on site.
| A Item | B Description of work | C Scheduled value | D From previous applications | E This period | F Materials stored | G Completed and stored (D+E+F) | % (G ÷ C) | H Balance to finish (C−G) | I Retainage (10%) |
|---|---|---|---|---|---|---|---|---|---|
| 1 | General conditions | $80,000 | $24,000 | $8,000 | $0 | $32,000 | 40.0% | $48,000 | $3,200 |
| 2 | Sitework and utilities | $95,000 | $95,000 | $0 | $0 | $95,000 | 100.0% | $0 | $9,500 |
| 3 | Concrete | $210,000 | $150,000 | $60,000 | $0 | $210,000 | 100.0% | $0 | $21,000 |
| 4 | Structural steel | $180,000 | $36,000 | $90,000 | $0 | $126,000 | 70.0% | $54,000 | $12,600 |
| 5 | Roofing | $70,000 | $0 | $0 | $18,000 | $18,000 | 25.7% | $52,000 | $1,800 |
| 6 | Mechanical (HVAC and plumbing) | $185,000 | $0 | $37,000 | $12,000 | $49,000 | 26.5% | $136,000 | $4,900 |
| 7 | Electrical | $145,000 | $0 | $29,000 | $0 | $29,000 | 20.0% | $116,000 | $2,900 |
| 8 | Finishes | $35,000 | $0 | $0 | $0 | $0 | 0.0% | $35,000 | $0 |
| 9 | CO-01 Parking-lot site lighting | $25,000 | $0 | $5,000 | $0 | $5,000 | 20.0% | $20,000 | $500 |
| Totals | $1,025,000 | $305,000 | $229,000 | $30,000 | $564,000 | 55.0% | $461,000 | $56,400 |
| Line | Item | Amount | How it is calculated |
|---|---|---|---|
| 1 | Original contract sum | $1,000,000 | From the signed contract |
| 2 | Net change by change orders | $25,000 | Approved change orders only (CO-01) |
| 3 | Contract sum to date | $1,025,000 | Line 1 ± line 2 |
| 4 | Total completed and stored to date | $564,000 | Column G total on the continuation sheet |
| 5a | Retainage on completed work (10%) | $53,400 | 10% × (columns D + E) |
| 5b | Retainage on stored material (10%) | $3,000 | 10% × column F |
| 5 | Total retainage | $56,400 | Lines 5a + 5b (column I total) |
| 6 | Total earned less retainage | $507,600 | Line 4 − line 5 |
| 7 | Less previous certificates for payment | $274,500 | Line 6 from application No. 2 |
| 8 | Current payment due | $233,100 | Line 6 − line 7 |
| 9 | Balance to finish, including retainage | $517,400 | Line 3 − line 6 |
Check the math the way an owner’s reviewer will: work this period plus newly stored material is $229,000 + $30,000 = $259,000. Less 10% retainage, that is $233,100 — the same as line 8. If those two numbers disagree, something in column D does not match the previous application.
How to fill out a G702 and G703, step by step
Start from the schedule of values, roll forward last period’s totals, enter this period’s progress and stored materials, then let the continuation sheet totals drive the one-page summary.
- 1
Step 1
Confirm the schedule of values: every line item and its scheduled value, with approved change orders added as their own lines, totaling the contract sum to date. - 2
Step 2
Fill column D (work completed on previous applications) with columns D + E from the last approved application, line by line. - 3
Step 3
Enter column E: the value of work completed on each line during this billing period, usually from a percent-complete walk with the project manager. - 4
Step 4
Enter column F: materials delivered and stored but not yet installed, with the invoices or bills of sale the owner requires. - 5
Step 5
Calculate column G (D + E + F), percent complete (G ÷ C), balance to finish (C − G) and retainage per line. - 6
Step 6
Carry the column totals to the summary: completed and stored to date, retainage on completed work and on stored material, total earned less retainage. - 7
Step 7
Subtract previous certificates for payment to get the current payment due, then sign, notarize if your contract requires it, and submit with backup and lien waivers.
Common G702/G703 mistakes that delay payment
Most rejected pay applications fail on arithmetic that does not tie to the previous application, billing for unapproved change orders, or missing backup and lien waivers.
- Column D does not match last month. Column D on each line should equal columns D + E from the previous approved application. Material stored last period and installed this period moves out of column F and into column E.
- Billing pending change orders. Only approved change orders belong on the sheet and in line 2.
- Front-loaded schedule of values. Over-valuing early line items gets challenged by the architect and can be rejected outright.
- Stored materials without backup. Owners usually require invoices, insurance and proof of storage location before paying column F.
- Wrong retainage basis. Retainage applies to completed work and stored material separately; some contracts reduce it after a completion milestone.
- Missing waivers. Many owners require a conditional waiver for this payment and unconditional waivers for the last one — see lien waivers.
Producing G702/G703-style pay applications in software
Pay application software keeps the schedule of values, previous billings, change orders and retainage in one place so each new application is calculated from the last one instead of retyped.
In Aequo Build, the AIA billing register creates a pay application from the job’s schedule of values, carries forward previous certificates, adds approved change orders, applies the job’s retainage rate (including step-down retainage schedules) and generates a G702/G703-style PDF for submission. See how other tools compare in our AIA billing software comparison.
Frequently asked questions
What is the difference between AIA G702 and G703?
G702 (Application and Certificate for Payment) is the one-page summary: contract sum, change orders, work completed and stored to date, retainage, previous certificates and the current payment due. G703 (Continuation Sheet) is the line-by-line schedule of values that supports those totals. You submit them together.
Who fills out the G702 and who certifies it?
The contractor completes and signs the application, has it notarized where required, and submits it with the G703 to the architect. The architect completes the certificate, may certify a different amount with an explanation, and the owner pays the contractor based on the amount certified.
Is there a free AIA G702 form?
No. AIA documents are copyrighted and sold by AIA Contract Documents; copying or retyping them without permission infringes their copyright. You can use your own pay application in a G702/G703-style layout — like the free template on this site — when your contract does not require the official AIA form.
How is retainage calculated on a G702?
Retainage is a percentage of the work completed to date (columns D + E of the continuation sheet) plus a percentage of stored materials (column F). The two are added for total retainage, which is subtracted from the total completed and stored to date to give total earned less retainage.
How are change orders shown on a G703?
Approved change orders are normally added as separate lines at the end of the continuation sheet or on their own sheet, and the net change is shown on the G702 summary. Pending or unapproved change orders are not billed.
Do subcontractors use the G702 and G703?
Many general contractors ask subcontractors for G702/G703-style pay applications so sub billing rolls up into the owner application. AIA also publishes subcontractor variations (G702S and G703S, 2017 editions). Your subcontract decides which form is required.
Run subcontractor invoices, pay apps and retainage in one place
Aequo Build is construction accounts payable for contractors on QuickBooks Online: invoice capture, approvals, lien-waiver payment holds, invoice-linked retainage and an AIA-style billing register.
Related guides and tools
- Free G702/G703-style pay application templatePrintable summary + continuation sheet, plus a CSV.
- Schedule of values guide and templateBuild the SOV that drives every pay application.
- Progress billing (and QuickBooks Online)Percent-complete billing, retainage and QBO progress invoicing.
- AIA billing software comparedProcore, Siteline, GCPay, Textura, Built and Aequo Build.
- Retainage calculatorModel retainage held and released over a contract.
- Lien waivers in construction APConditional vs unconditional waivers and payment holds.
Sources
Checked on October 21, 2026. Vendor capabilities and prices change; confirm current details with each vendor.
- AIA Contract Documents — Instructions: G702–1992, Application and Certificate for Payment — purpose, contractor signs and notarizes, architect certifies, owner pays the certified amount
- AIA Contract Documents — Summary: G702–1992 — used where the contractor has a direct agreement with the owner; procedures in A201
- AIA Contract Documents — G702–1992 sample (preview PDF) — summary line items 1–9
- AIA Contract Documents — G703–1992 sample (preview PDF) — continuation sheet columns A–I
- AIA Contract Documents — Instructions: G703–1992, Continuation Sheet — columns follow the schedule of values; change orders listed separately; column I for variable retainage
- AIA Contract Documents — FAQ: related payment application forms — G702S/G703S, G702CW, G702GMP, G732, G742
- AIA Contract Documents — FAQ: copying AIA Contract Documents — documents are copyrighted; copying or retyping without permission infringes
- AIA Contract Documents — G702 Pay Application — sold as a one-time-use document or by subscription
- AIA Contract Documents (learn) — What is a schedule of values and why is it required? — A201–2017 §9.2 requires a schedule of values before the first application for payment