AIA G702 and G703, explained with a worked example

AIA G702 is the Application and Certificate for Payment — a one-page summary a contractor submits to bill an owner for work completed — and AIA G703 is the Continuation Sheet that breaks the contract into schedule-of-values line items. Together they show what has been earned, how much retainage is held, what was already paid and the current payment due.
Below: what each document contains, line by line; a filled-in example for a fictional $1,025,000 project; and the most common mistakes. Need a blank form? Use our free G702/G703-style pay application template.

Last updated · Aequo AP editorial team

What is the AIA G702?

The G702 (current edition G702–1992) is a one-page application in which the contractor states how much of the contract has been earned and how much is due now, and the architect certifies the amount the owner should pay.

AIA describes G702 as serving as both the contractor’s application and the architect’s certification. It is designed for projects where the contractor has a direct agreement with the owner, with payment procedures set out in AIA A201, General Conditions. The contractor signs it (and has it notarized where the contract calls for that), attaches the G703 and submits both to the architect. The architect may certify a different amount — initialing changed figures and attaching an explanation — and the owner pays the contractor the amount certified.

The nine lines of the G702 summary
LineWhat it showsWhere the number comes from
1Original contract sumThe signed contract
2Net change by change ordersApproved change orders (additions minus deductions)
3Contract sum to dateLine 1 ± line 2
4Total completed and stored to dateColumn G total on the G703
5Retainage — (a) % of completed work, (b) % of stored material5a from G703 columns D + E; 5b from column F; total = column I total
6Total earned less retainageLine 4 − line 5 total
7Less previous certificates for paymentLine 6 from the prior certificate
8Current payment dueLine 6 − line 7
9Balance to finish, including retainageLine 3 − line 6
Line names paraphrased from AIA’s G702–1992 sample. The form also carries a change order summary, the contractor’s signature and notary block, and the architect’s certificate with the amount certified.

What is the AIA G703?

The G703 Continuation Sheet lists each line of the schedule of values and tracks, per line, what has been billed before, what is billed this period, materials stored, percent complete, balance to finish and retainage.

AIA’s instructions say columns A–C should match the schedule of values the contractor submitted at the start of the project. Approved change orders are usually listed separately, at the end of the basic schedule or on their own sheet. Column I (retainage) is normally used only when the contract allows a different retainage rate per line.

G703 continuation sheet columns
ColumnMeaning
AItem number
BDescription of work
CScheduled value
DWork completed — from previous applications
EWork completed — this period
FMaterials presently stored (not in D or E)
GTotal completed and stored to date (D + E + F)
%Percent complete (G ÷ C)
HBalance to finish (C − G)
IRetainage (if variable rate)

Worked example: a filled-in G702/G703-style pay application

On application No. 3 for a $1,025,000 contract with 10% retainage, the contractor has completed and stored $564,000 of work, holds $56,400 in retainage, was previously certified $274,500, and is owed $233,100 this period.

The project is fictional: an original contract of $1,000,000, one approved change order for $25,000 (parking-lot lighting) and 10% retainage on both completed work and stored materials. Two applications have already been paid. This period the contractor completed steel, concrete, MEP rough-in and part of the change-order work, and has roofing and mechanical equipment stored on site.

Continuation sheet — Application No. 3, period to September 30, 2026
A
Item
B
Description of work
C
Scheduled value
D
From previous applications
E
This period
F
Materials stored
G
Completed and stored (D+E+F)
%
(G ÷ C)
H
Balance to finish (C−G)
I
Retainage (10%)
1General conditions$80,000$24,000$8,000$0$32,00040.0%$48,000$3,200
2Sitework and utilities$95,000$95,000$0$0$95,000100.0%$0$9,500
3Concrete$210,000$150,000$60,000$0$210,000100.0%$0$21,000
4Structural steel$180,000$36,000$90,000$0$126,00070.0%$54,000$12,600
5Roofing$70,000$0$0$18,000$18,00025.7%$52,000$1,800
6Mechanical (HVAC and plumbing)$185,000$0$37,000$12,000$49,00026.5%$136,000$4,900
7Electrical$145,000$0$29,000$0$29,00020.0%$116,000$2,900
8Finishes$35,000$0$0$0$00.0%$35,000$0
9CO-01 Parking-lot site lighting$25,000$0$5,000$0$5,00020.0%$20,000$500
Totals$1,025,000$305,000$229,000$30,000$564,00055.0%$461,000$56,400
Application summary — Riverside Medical Office Building (fictional), Application No. 3
LineItemAmountHow it is calculated
1Original contract sum$1,000,000From the signed contract
2Net change by change orders$25,000Approved change orders only (CO-01)
3Contract sum to date$1,025,000Line 1 ± line 2
4Total completed and stored to date$564,000Column G total on the continuation sheet
5aRetainage on completed work (10%)$53,40010% × (columns D + E)
5bRetainage on stored material (10%)$3,00010% × column F
5Total retainage$56,400Lines 5a + 5b (column I total)
6Total earned less retainage$507,600Line 4 − line 5
7Less previous certificates for payment$274,500Line 6 from application No. 2
8Current payment due$233,100Line 6 − line 7
9Balance to finish, including retainage$517,400Line 3 − line 6

Check the math the way an owner’s reviewer will: work this period plus newly stored material is $229,000 + $30,000 = $259,000. Less 10% retainage, that is $233,100 — the same as line 8. If those two numbers disagree, something in column D does not match the previous application.

How to fill out a G702 and G703, step by step

Start from the schedule of values, roll forward last period’s totals, enter this period’s progress and stored materials, then let the continuation sheet totals drive the one-page summary.

  1. 1

    Step 1

    Confirm the schedule of values: every line item and its scheduled value, with approved change orders added as their own lines, totaling the contract sum to date.
  2. 2

    Step 2

    Fill column D (work completed on previous applications) with columns D + E from the last approved application, line by line.
  3. 3

    Step 3

    Enter column E: the value of work completed on each line during this billing period, usually from a percent-complete walk with the project manager.
  4. 4

    Step 4

    Enter column F: materials delivered and stored but not yet installed, with the invoices or bills of sale the owner requires.
  5. 5

    Step 5

    Calculate column G (D + E + F), percent complete (G ÷ C), balance to finish (C − G) and retainage per line.
  6. 6

    Step 6

    Carry the column totals to the summary: completed and stored to date, retainage on completed work and on stored material, total earned less retainage.
  7. 7

    Step 7

    Subtract previous certificates for payment to get the current payment due, then sign, notarize if your contract requires it, and submit with backup and lien waivers.

Common G702/G703 mistakes that delay payment

Most rejected pay applications fail on arithmetic that does not tie to the previous application, billing for unapproved change orders, or missing backup and lien waivers.

  • Column D does not match last month. Column D on each line should equal columns D + E from the previous approved application. Material stored last period and installed this period moves out of column F and into column E.
  • Billing pending change orders. Only approved change orders belong on the sheet and in line 2.
  • Front-loaded schedule of values. Over-valuing early line items gets challenged by the architect and can be rejected outright.
  • Stored materials without backup. Owners usually require invoices, insurance and proof of storage location before paying column F.
  • Wrong retainage basis. Retainage applies to completed work and stored material separately; some contracts reduce it after a completion milestone.
  • Missing waivers. Many owners require a conditional waiver for this payment and unconditional waivers for the last one — see lien waivers.

Producing G702/G703-style pay applications in software

Pay application software keeps the schedule of values, previous billings, change orders and retainage in one place so each new application is calculated from the last one instead of retyped.

In Aequo Build, the AIA billing register creates a pay application from the job’s schedule of values, carries forward previous certificates, adds approved change orders, applies the job’s retainage rate (including step-down retainage schedules) and generates a G702/G703-style PDF for submission. See how other tools compare in our AIA billing software comparison.

Frequently asked questions

What is the difference between AIA G702 and G703?

G702 (Application and Certificate for Payment) is the one-page summary: contract sum, change orders, work completed and stored to date, retainage, previous certificates and the current payment due. G703 (Continuation Sheet) is the line-by-line schedule of values that supports those totals. You submit them together.

Who fills out the G702 and who certifies it?

The contractor completes and signs the application, has it notarized where required, and submits it with the G703 to the architect. The architect completes the certificate, may certify a different amount with an explanation, and the owner pays the contractor based on the amount certified.

Is there a free AIA G702 form?

No. AIA documents are copyrighted and sold by AIA Contract Documents; copying or retyping them without permission infringes their copyright. You can use your own pay application in a G702/G703-style layout — like the free template on this site — when your contract does not require the official AIA form.

How is retainage calculated on a G702?

Retainage is a percentage of the work completed to date (columns D + E of the continuation sheet) plus a percentage of stored materials (column F). The two are added for total retainage, which is subtracted from the total completed and stored to date to give total earned less retainage.

How are change orders shown on a G703?

Approved change orders are normally added as separate lines at the end of the continuation sheet or on their own sheet, and the net change is shown on the G702 summary. Pending or unapproved change orders are not billed.

Do subcontractors use the G702 and G703?

Many general contractors ask subcontractors for G702/G703-style pay applications so sub billing rolls up into the owner application. AIA also publishes subcontractor variations (G702S and G703S, 2017 editions). Your subcontract decides which form is required.

Run subcontractor invoices, pay apps and retainage in one place

Aequo Build is construction accounts payable for contractors on QuickBooks Online: invoice capture, approvals, lien-waiver payment holds, invoice-linked retainage and an AIA-style billing register.

Sources

Checked on October 21, 2026. Vendor capabilities and prices change; confirm current details with each vendor.

  1. AIA Contract Documents — Instructions: G702–1992, Application and Certificate for Payment — purpose, contractor signs and notarizes, architect certifies, owner pays the certified amount
  2. AIA Contract Documents — Summary: G702–1992 — used where the contractor has a direct agreement with the owner; procedures in A201
  3. AIA Contract Documents — G702–1992 sample (preview PDF) — summary line items 1–9
  4. AIA Contract Documents — G703–1992 sample (preview PDF) — continuation sheet columns A–I
  5. AIA Contract Documents — Instructions: G703–1992, Continuation Sheet — columns follow the schedule of values; change orders listed separately; column I for variable retainage
  6. AIA Contract Documents — FAQ: related payment application forms — G702S/G703S, G702CW, G702GMP, G732, G742
  7. AIA Contract Documents — FAQ: copying AIA Contract Documents — documents are copyrighted; copying or retyping without permission infringes
  8. AIA Contract Documents — G702 Pay Application — sold as a one-time-use document or by subscription
  9. AIA Contract Documents (learn) — What is a schedule of values and why is it required? — A201–2017 §9.2 requires a schedule of values before the first application for payment