Construction WIP report template

This free WIP report template calculates percent complete (cost to date ÷ estimated total cost), earned revenue, and over or under billing for each open job. Download the CSV with formulas, or print the blank worksheet below.

Last updated · Aequo AP editorial team

Printable WIP worksheet

Fill one row per open job. Calculate the shaded columns with the formulas underneath.

JobContract valueEst. total costEst. gross profitCost to date% completeEarned revenueBilled to dateOver billingUnder billingCost to complete
Totals
ColumnFormula
Est. gross profitContract value − est. total cost
% completeCost to date ÷ est. total cost
Earned revenueContract value × % complete
Over billingBilled to date − earned revenue, if positive
Under billingEarned revenue − billed to date, if positive
Cost to completeEst. total cost − cost to date

How to use the template

Update it monthly, after the month’s bills are coded and posted and project managers have re-estimated cost to complete.

  1. 1
    Download the CSV and open it in Excel or Google Sheets; the formulas calculate automatically.
  2. 2
    Replace the two example jobs with your open jobs. Add rows above the Totals row and copy the formulas down.
  3. 3
    Enter contract value including approved change orders, the current estimated total cost, cost to date, and billed to date.
  4. 4
    Review percent complete, earned revenue, and over/under billing for each job, then the totals.
  5. 5
    Save a copy each month so you can see how estimates and over/under balances move over time.

Where the inputs come from

Contract value and billed to date come from your contracts and progress billings; cost to date comes from the job-cost ledger; estimated total cost comes from the project manager.

The template is only as good as cost to date, which depends on every vendor bill being coded to the right job before month-end. For the full explanation of the report, see WIP reports in construction.

Frequently asked questions

Which percent-complete method does the template use?

Cost-to-cost: cost to date divided by estimated total cost. If your CPA uses a different method for some contracts, overwrite the % complete column for those jobs.

Should billed to date include retainage?

Yes. Use gross billings before retainage is withheld; retainage changes when you collect, not what you have billed.

Can I use the template with QuickBooks Online?

Yes. Export costs and billings by customer or project from QuickBooks Online, then paste the totals per job into the template.

Related guides and tools

Sources

Template provided for general use; it is not accounting or tax advice. Confirm your revenue recognition method with your CPA.

  1. 26 U.S. Code § 460 — Special rules for long-term contracts (Cornell LII)
  2. Wiss — ASC 606 Implementation for Construction Contractors

Run construction AP on QuickBooks Online

Aequo Build is the construction AP layer on top of QuickBooks Online: invoice capture, job-cost coding, approvals, lien waivers, retainage holds, and subcontractor compliance checks before payment.

Part of the Construction AP Knowledge Centre.