Match each subcontractor invoice to its subcontract, then check it against the revised subcontract value: the original value plus approved change orders only, minus everything already billed. Billed lines should tie to the schedule of values, including lines added by approved change orders. Anything billed against a change order that is still pending is held until the change order is approved or rejected.

Last updated · Aequo AP editorial team

The rule in one line

A subcontractor can be paid for the original scope plus approved change orders, up to the revised subcontract value, less what has already been billed and less retainage. Pending change orders do not count yet.

What you are matching a subcontractor invoice against

Three records: the subcontract (the original commitment), the approved change orders that adjust it, and the billing history that shows how much of it has already been invoiced.

RecordWhat it tells youCheck on each invoice
SubcontractOriginal value, scope, retainage rate, jobRight subcontractor, right job, right subcontract number
Approved change ordersSigned increases or decreases to the subcontract value and timeOnly approved change orders raise what can be billed
Schedule of valuesHow the value splits into billable linesEach billed line is within its scheduled value
Billing historyBilled to date and remaining balanceThis invoice fits inside the remaining balance

Subcontract change orders are signed by both the contractor and the subcontractor. On the AIA subcontract change order form (G701S), signing records agreement on all terms of the change, including the new subcontract sum and any change in time. A construction change directive is not part of the subcontract sum until it has been agreed and recorded as a change order.

How to match the invoice, step by step

Identify the subcontract, recalculate its revised value from approved change orders, confirm the invoice fits the remaining balance, check the lines, hold unapproved change-order work, then apply retainage.

  1. 1
    Find the subcontract the invoice bills against: the subcontract number, job and subcontractor should all agree.
  2. 2
    Work out the revised subcontract value: the original value plus every approved change order, and nothing that is still pending.
  3. 3
    Subtract what has already been billed to get the remaining balance, and confirm the invoice fits inside it.
  4. 4
    Check each billed line against its schedule-of-values line, including the lines added or increased by approved change orders.
  5. 5
    Hold any amount billed against a change order that has not been approved, and send the rest through approval.
  6. 6
    Calculate retainage on the approved amount at the subcontract’s rate, then update billed-to-date and the remaining balance.

The line check matters as much as the total. A subcontractor can stay inside the overall balance while billing one line past its scheduled value, which usually means a change order has been billed before it was approved, or base-scope work has been billed twice. See the schedule of values guide for how lines are set up and how approved change orders are added.

Worked example: a progress bill that includes change-order work

An electrical subcontract of $480,000 with one approved change order of $36,000 has a revised value of $516,000. After $310,000 billed to date, $206,000 remains, so a bill for approved work of $52,000 fits; the $9,500 billed on a pending change order is held.

ItemAmountTreatment
Original subcontract value$480,000Executed subcontract
CO-03, added circuits (approved)$36,000Counts toward the revised value
CO-04, relocated panel (pending)$9,500Not counted until approved
Revised subcontract value$516,000Original plus approved change orders
Billed to date before this invoice$310,000From prior approved bills
Remaining before this invoice$206,000Revised value minus billed to date

The subcontractor’s invoice for the period bills three amounts:

Invoice lineBilledDecision
Base scope, rough-in (schedule-of-values line 4)$34,000Approve: within the line and the balance
CO-03 added circuits$18,000Approve: change order is approved and the line has room
CO-04 relocated panel$9,500Hold: change order not yet approved
  • Approved for payment: $34,000 + $18,000 = $52,000.
  • Retainage at 10%: $5,200, so the net payable now is $46,800.
  • Billed to date becomes $362,000 and the remaining balance $154,000.
  • If CO-04 is approved later, the revised value rises to $525,500 and the held $9,500 can be approved on its own or rebilled.

Work out the hold with the retainage calculator, and see what retainage is for how it is released.

Common mismatches and what to do about them

Most problems come from timing: change-order work billed before the change order is signed, change orders counted twice, or a subcontract value that was never updated after a change was approved.

MismatchUsual causeWhat to do
Invoice bills a change order you cannot find as approvedWork started on a verbal go-ahead or a pending change orderHold that amount; approve or reject the change order, then release
Invoice total exceeds the remaining balanceApproved change order not yet entered on the subcontract, or overbillingCheck the change-order log first; if nothing is missing, short-pay or return the bill
A line bills past its scheduled valueChange-order work billed against a base lineAsk the subcontractor to bill the change order on its own line
Change order approved with the owner but not with the subThe owner-side change was never issued to the subcontractorIssue the subcontract change order before approving the bill
Retainage looks wrongRetainage calculated on the gross bill including held amountsCalculate retainage only on the amount approved for payment

Should you pay for work on a pending change order?

Not through the subcontract until the change order is approved, unless your subcontract allows payment for directed work in another way. Hold the amount, keep the work moving, and settle the change order quickly so the subcontractor is not financing your paperwork.

Slow change-order approval is a common reason subcontractor bills get stuck. If change orders routinely sit for weeks, fix the approval route for change orders rather than paying around it. The subcontractor invoice workflow with Procore and QuickBooks covers who should own each step when project management and accounting live in different systems.

Aequo Build

How Aequo Build matches subcontractor invoices to subcontracts and change orders

Each subcontract in Aequo Build records the job, subcontractor, original value, retainage rate, approved changes, revised value and remaining balance. A change order is entered against a job, can be linked to one subcontract or purchase order, carries an optional markup, and must be allocated across lines of the job’s schedule of values so the allocations add up to the change-order total.

Approving a change order requires approval permission and updates everything in one step: the linked subcontract’s approved changes, revised value and remaining balance, the schedule-of-values lines, the job’s contract value, and the committed cost on the cost code. Rejecting one requires a reason, which is kept in the audit trail. Pending change orders do not change the subcontract value.

When a subcontractor invoice arrives without a purchase order, Aequo Build looks for that subcontractor’s active subcontract using the subcontract number on the invoice, the scope and job, and whether the amount fits the remaining or revised value. The match records which subcontract it was checked against, anything outside tolerance goes to review, and when the bill clears, billed-to-date and the remaining balance on the subcontract update. After a change order is approved, open exceptions on that job’s purchase orders are re-checked automatically.

The check is made against the subcontract as a whole, so a reviewer still compares the invoice lines with the schedule of values. Aequo Build connects to QuickBooks Online today; Procore and QuickBooks Desktop connections are in development.

Frequently asked questions

How do I match a subcontractor invoice to a subcontract?

Confirm the subcontract number, job and subcontractor, then check the invoice against the revised subcontract value (original plus approved change orders) minus what has already been billed. Check each line against the schedule of values and hold anything billed on a change order that is not yet approved.

What is the revised subcontract value?

The original subcontract value plus the net total of approved change orders. Pending or proposed change orders are not included until they are approved.

Can a subcontractor bill for a change order before it is approved?

They can submit the bill, but the amount should be held until the change order is approved. Paying it early removes your leverage to settle the price and leaves the subcontract value out of step with what you have paid.

Should change-order work be billed on its own line?

Yes. Ask subcontractors to bill each approved change order on its own schedule-of-values line. It keeps the base scope and the change separate, makes percent complete checkable, and shows whether the change order has been billed in full.

Is retainage withheld on change-order work?

Usually, at the same rate as the rest of the subcontract, unless the subcontract or the change order says otherwise. Calculate it only on the amount approved for payment.

Does Aequo Build work with Procore change orders?

Not yet. The Procore connection is in development. Today change orders are entered in Aequo Build, which connects to QuickBooks Online.

Related guides and tools

Sources

This guide is general information, not legal advice. What a subcontractor can bill for, and when, depends on your subcontract and change-order terms.

  1. AIA Contract Documents — Instructions: G701S–2017, Change Order (subcontract)
  2. AIA Contract Documents — Instructions: G702–1992, Application and Certificate for Payment

Part of the Construction AP Knowledge Centre.