Why the schedule of values matters
The schedule of values is the payment contract in table form: every progress payment, retainage calculation and balance to finish is computed from it.
Under AIA A201–2017 §9.2, for stipulated-sum and guaranteed-maximum-price contracts, the contractor submits a schedule of values allocating the entire contract sum before the first application for payment. Once approved, it is used to evaluate each application. AIA does not publish a standard SOV form; the G703 Continuation Sheet is commonly used to record it.
- For the owner or GC: it makes overbilling visible — no line can be billed past 100% of its value.
- For the contractor: a clear SOV gets pay applications approved faster, with fewer back-and-forth questions.
- For accounting: mapped to cost codes, it connects billing to job costing and WIP reporting.
Schedule of values example
Here is a $1,025,000 schedule of values for a fictional medical office building: eight base-contract lines plus one approved change order, each mapped to a cost code.
| Item | Cost code | Description of work | Scheduled value | % of contract |
|---|---|---|---|---|
| 1 | 01-000 | General conditions | $80,000 | 7.8% |
| 2 | 02-000 | Sitework and utilities | $95,000 | 9.3% |
| 3 | 03-000 | Concrete | $210,000 | 20.5% |
| 4 | 05-100 | Structural steel | $180,000 | 17.6% |
| 5 | 07-500 | Roofing | $70,000 | 6.8% |
| 6 | 23-000 | Mechanical (HVAC and plumbing) | $185,000 | 18.0% |
| 7 | 26-000 | Electrical | $145,000 | 14.1% |
| 8 | 09-000 | Finishes | $35,000 | 3.4% |
| 9 | CO-01 | CO-01 Parking-lot site lighting | $25,000 | 2.4% |
| Total contract sum to date | $1,025,000 | 100.0% |
How to create a schedule of values
Break the contract sum into verifiable lines of work, price each from your estimate without front-loading, and make the lines total the contract sum exactly.
- 1
Step 1
Start from the contract sum and your estimate, broken down the way the work will be performed and inspected. - 2
Step 2
Create one line per trade, phase or system — by CSI division, building area or floor — at a level the owner can verify in the field. - 3
Step 3
Assign each line a scheduled value from the estimate, spreading overhead, profit and general conditions honestly rather than loading early lines. - 4
Step 4
Separate long-lead materials that will be stored before installation, so stored-material billing is easy to support. - 5
Step 5
Check that the lines add up exactly to the contract sum, and map each line to your job cost codes. - 6
Step 6
Submit the schedule of values for approval before the first pay application, then add approved change orders as new lines.
Free schedule of values template
Print this blank template, or download the CSV (pre-filled with the example above, with percent-of-contract formulas).
Schedule of Values
Template by Aequo AP (aequoap.com). Project: ______________________ Contract sum: $____________ Date: __________
| Item | Cost code | Description of work | Scheduled value | % of contract | Notes |
|---|---|---|---|---|---|
| 1 | |||||
| 2 | |||||
| 3 | |||||
| 4 | |||||
| 5 | |||||
| 6 | |||||
| 7 | |||||
| 8 | |||||
| 9 | |||||
| 10 | |||||
| 11 | |||||
| 12 | |||||
| 13 | |||||
| 14 | |||||
| 15 | |||||
| 16 | |||||
| Total (must equal contract sum) | 100% |
Submitted by: ______________________ Approved by: ______________________ Date: __________
How the schedule of values drives progress billing
Each billing period, the contractor reports percent complete (or dollars earned) against every SOV line; the sum of those lines, less retainage and previous payments, is the amount due.
On a G703-style continuation sheet, the SOV supplies columns A–C (item, description, scheduled value), and each period adds work completed, stored materials, percent complete, balance to finish and retainage. See the full arithmetic in our worked G702/G703 example, and how percent-complete billing works in progress billing.
Schedule of values in Procore
In Procore, SOVs live on contracts: the prime contract with the owner and each commitment (subcontract or purchase order), and subcontractors can add a more detailed Subcontractor SOV that carries through to their invoices.
- Commitment SOV. Each commitment has a Schedule of Values tab that matches the approved agreement.
- Subcontractor SOV. Enabled on the Commitments tool by default, it lets a downstream contractor break their contract into more detailed lines while the commitment SOV stays consistent with the agreement. It works only with the amount-based accounting method, and only the detail lines on the Subcontractor SOV carry over to the invoice — so they must be in place before the sub invoices.
- Invoicing. Procore’s Invoicing tool generates owner and subcontractor invoices against these SOVs by billing period, including retainage, and the legacy owner-invoice export produces an “Application and Certificate for Payment” PDF.
- Accounting sync. Procore notes the Subcontractor SOV does not sync to an integrated ERP — only the commitment’s general SOV does. With Procore’s own QuickBooks Online connector, commitments and prime contracts are not synced at all; subcontractor invoices sync as bills.
Schedules of values in Aequo Build
Aequo Build stores a schedule of values per job and uses it to create each AIA-style pay application, so the SOV, approved change orders, retainage and previous certificates stay in one record.
Line items can be added or updated as the job changes, and each new pay application starts from the current SOV with previous billings carried forward. See Aequo Build.
Frequently asked questions
What is a schedule of values in construction?
A schedule of values (SOV) is a list that divides the contract sum into line items of work — by trade, phase or system — each with a dollar value. The lines add up to the contract sum and become the basis for every progress billing and pay application on the project.
Who prepares the schedule of values?
The contractor prepares it and submits it for approval. Under AIA A201–2017, the contractor submits a schedule of values allocating the entire contract sum before the first application for payment on stipulated-sum and GMP contracts; subcontractors prepare one for their subcontract in the same way.
Is there an official AIA schedule of values form?
No. AIA does not publish a standard schedule of values form. The G703 Continuation Sheet is often used to record the submitted schedule of values, because its columns follow it line by line.
How detailed should a schedule of values be?
Detailed enough that the owner or GC can verify percent complete in the field, but not so detailed that billing becomes a bookkeeping exercise. Check the contract and specifications: owners and architects often set a minimum level of detail, such as one line per specification section.
What is front-loading a schedule of values?
Front-loading is assigning more value to early work (mobilization, sitework, foundations) than it is worth so the contractor is paid ahead of progress. Reviewers look for it, and it can lead to a rejected schedule of values or reduced payments.
How do change orders affect the schedule of values?
Approved change orders are added as new lines (or listed separately) so the schedule of values always totals the current contract sum. Pending change orders are not billed.
Run subcontractor invoices, pay apps and retainage in one place
Aequo Build is construction accounts payable for contractors on QuickBooks Online: invoice capture, approvals, lien-waiver payment holds, invoice-linked retainage and an AIA-style billing register.
Related guides and tools
- AIA G702 and G703 explainedHow the SOV becomes a pay application.
- Pay application templateFree G702/G703-style template and CSV.
- Progress billing guideBill against the SOV, including in QuickBooks Online.
- Procore + QuickBooks: who processes sub invoices?Where commitments, SOVs and AP approval live.
- Job costing for contractorsMap SOV lines to cost codes.
- Change order (glossary)How scope changes reach the contract sum.
Sources
Checked on October 21, 2026. Vendor capabilities and prices change; confirm current details with each vendor.
- AIA Contract Documents (learn) — What is a schedule of values and why is it required on construction projects? — A201–2017 §9.2; G703 often used to record the SOV
- AIA Contract Documents — Summary: G702–1992 — “The AIA does not publish a standard schedule of values form.”
- AIA Contract Documents — Instructions: G703–1992, Continuation Sheet — columns A–C consistent with the submitted SOV; change orders listed separately
- Procore Support — Add a Subcontractor SOV to a commitment — Subcontractor SOV tab, amount-based only, carries to invoices, does not sync to ERP
- Procore Support — Invoicing — owner and subcontractor invoices, billing periods, retainage
- Procore Support — Export a configurable PDF of an owner invoice — generates an “Application and Certificate for Payment” PDF (legacy)
- Procore Support — QuickBooks Online integration — commitments and prime contracts are not synced to QuickBooks Online